Installing Primary AC Power, Continued
Install AC power wiring to the PECM connectors TB1, TB2, and TB10 as specified in the
Application Drawing Package, Block & Utility sheet. TB10 is used for AC input to power the
electronics enclosure. In the standard configuration TB10 is connected to TB1. Optionally, TB10
may be isolated from TB1 and connected to a separate UPS as specified in the drawing package.
TB1 - AC
Power Circuit
1
H N G
TB10 – AC
Power Input for
Electronics
(Optional UPS)
H N G
TB2 - AC
Power Circuit
2
H N G
Location of fuses. See description of correct fuses on following page.
21