Application
3.14 Shipping
30
Before moving the converter boxes to their final installation site, it is recommended that the cable for the
DC input and the AC main power connection are first routed and prepared. Since the cables are very
rigid, moving and connecting them after cabinet installation can be very difficult.
The inverter cabinets are mounted on transport pallets as standard. They can thus be moved by forklift or
pallet truck.