Before turning On The Power After Installation:
After completing machine installation, check the following
points before turning ON the power
(1) Make sure that all bolts are tightened securely
(2) Make sure that all connectors are connected securely
(3) Make sure that all hydraulic hoses and air pipes are
connected securely.
(4) If the machine is equipped with any optional external
equipment (bar feeder, loader, robot), make sure that each
electrical cable and hydraulic/pneumatic pipes are
connected correctly.
(5) Check the input voltage and all the L1/L2/L3 (R/S/T)
phases of input power.
After Turning ON The Power After Installation:
(a) Never feed the axes right away after turning ON the
power; manually operate the cycle pump to supply
lubricating oil to the slideway surfaces first.
(b) Check for oil leaks. Make sure that all of the gauges
indicate the correct values.
(c) Make sure that any transit clamps left in the machine are
removed.
(d) Repeatedly open and close the chuck to break in the
chuck operation cylinder. Then, break in the spindle.